Risk Management for "Dubai Eye" Project example

Haven't found the essay you need?

We can write it for you. On time. 100% original.

Order Now
Text Preview

Risk Management for "Dubai Eye" Project

Risk Identification

Risk identification is the second stage of risk management of any project that follows elaboration of risk management plan. The process of risk identification should be performed with a significant degree of efforts as unforeseen risks can put the well-planned project on the verge of the failure.

The following procedures are recommended to speed up the process: brainstorming, Delphi technique, interviewing, root cause analysis (Rose, 2013). The project team has performed few of these procedures, and the results of their efforts can be found in Table 1.

Table 1. Identified Risks and their Description

Risk

Risk Description

Technology Challenges

Dubai Eye is naturally an innovative construction that upon completion will be the highest observation wheel in the world. Typically, such endeavours raise a multitude of technological challenges to be solved. Thus, the technologies involved both in its construction and future usage are central for the successful project completion. Provided the solution is not found or prove to be inappropriate the project completion is under threat.

Foreign Exchange

Since not all companies involved in the construction of Dubai Eye are from the UAE, the problem of exchange rate fluctuation can increase the project cost.

Schedule Change

The risk of delays of different kinds present in projects of a different kind. Since Dubai Eye requires the cooperation of many contractors, the delay of one procedure can cause cascade delays of the dependent ones thus increasing project costs and postponing completion date.

Increase in Costs

The increase in costs is a potential problem for any innovative construction as to solve the unsolved challenges the project team should invest more resources that usual.

Environment Damage

Since the project scale is quite significant and potentially harmful for environment materials are used, it is primary to ensure that the handling of them as well as the performing of the hazardous operations is done properly or minimized.

Funding Problems

Dubai Eye is a breakthrough construction that requires massive investments. The fluctuation of the costs may need additional financing.

Wrong Estimation

The project team estimate of costs, reliability of contractors and suppliers, completion date, may vary significantly from actual ones.

Contractors and Suppliers

Contractors and Suppliers may be unwilling or unable to perform the procedures under the contract. Though the forfeit will be paid, there will be none to finish the project

Identified Risks Categorized by WBS

The generic project stages include planning, realization, and closing phases. These stages are high-level units in work-based structure, and Table 2 shows to which of them each risk belong.

Table 2. Identified Risks Categorized by WBS

Risk

Planning

Realization

Closing

Technology Challenges

Foreign Exchange

Schedule Change

Increase in Costs

Environment Damage

Funding Problems

Wrong Estimation

Contractors and Suppliers

Risk Consequences

To prioritize risks, the project manager should assess two parameters: its probability and the impact it might have on the project(Rose, 2013).

Table 3. The Probabilities of Identified Risks and their Rationale

Risk

Rationale

Probability

Technology Challenges

This …

Download Full Essay Show full preview

Disclaimer

Examples provided by Homework Lab are intended for the motivation and research purposes only. Do not submit any paper as your own piece of work. Every essay example belongs to students, who hold the copyright for the written content. Please, mind that the samples have been submitted to the Turnitin before and may show plagiarism in case of the repeated submission. Homework Lab does not bear any responsibility for the unauthorized submission of the examples.